# Kickoff Meeting — Treasury Modernization Support (TMS-2)

**Date:** February 19, 2025
**Location:** Treasury Annex, Bldg 1500, Conference Room 4B (hybrid; Teams link below)
**Note-taker:** J. Ortega, PM (Cascade Federal Services)

---

## Attendees

**Treasury / Customer side**
- Ms. Karen L. Stein — Contracting Officer (CO) — karen.stein@treasury.example.gov
- Mr. Tomas Friedrich — COR — tomas.friedrich@treasury.example.gov
- Mr. Andre Davies — Branch Chief, Modernization & Innovation Office
- Ms. Priya Subramanian — Tech lead, Office of the CIO

**Cascade Federal Services LLC (prime)**
- Jessica Ortega — Program Manager
- Marcus Lin — Technical Director
- Anika Roberts — Cybersecurity Lead
- Daniel Wong — Solutions Architect

---

## Contract Snapshot

| Field | Value |
|---|---|
| Contract Number | TR-OPM-25-D-0011 / Task Order 0001 |
| Vehicle | Treasury Acquisition Institute (TAI) BPA |
| Period of Performance | **February 17, 2025 — February 16, 2028** (base + two option years; option exercise TBD) |
| Total Ceiling Value | $11,800,000 (firm-fixed-price) |
| Status | **ACTIVE — performance period began 2025-02-17** |
| NAICS | 541512 |
| Set-Aside | Total Small Business |

---

## Discussion Topics

### 1. Welcome and introductions

Customer team welcomed Cascade aboard. Mr. Davies emphasized that this is a high-visibility modernization effort under direct review from the Deputy Secretary's office. Cascade's prior performance on the VA Patient Records Integration work (see CPARS narrative for that contract) was specifically called out by Ms. Stein during contractor selection.

### 2. Scope review

Three primary work streams over the 36-month period of performance:

1. **Legacy mainframe assessment** — inventory of 11 in-scope mainframe applications, decommissioning roadmap.
2. **Cloud target-state architecture** — design and prototype migration of two pilot applications to Treasury's approved cloud environment.
3. **Cybersecurity hardening** — ATO/RMF support for migrated systems, FedRAMP alignment.

### 3. Performance status

Performance has *just begun* — no completed milestones yet. The first major milestone is the Mainframe Inventory Report, due May 30, 2025 (approximately 100 days from kickoff).

### 4. Reporting cadence

Weekly status (Tuesday 10am ET), monthly written report due first business day of each month, quarterly executive review.

### 5. Risks raised

- Onboarding clearances for 3 of 9 staff still in process. Cascade will provide weekly clearance status until all are seated.
- Treasury's pilot cloud environment is awaiting a configuration change (ETA April). Pilot migration work may slip 2-3 weeks if not resolved by then.

### 6. Action items

| # | Owner | Action | Due |
|---|---|---|---|
| 1 | Ortega (Cascade) | Submit final org chart with cleared/uncleared status | 2025-02-26 |
| 2 | Roberts (Cascade) | Initial cybersecurity work plan draft | 2025-03-07 |
| 3 | Friedrich (Treasury) | Confirm pilot environment readiness date | 2025-03-15 |
| 4 | Lin (Cascade) | Submit mainframe inventory approach | 2025-03-21 |

---

**Internal note (Cascade):** Because this is a 36-month POP with significant ceiling value, this engagement will become a strong past-performance reference once we complete the base year and have at least one CPARS interim or annual rating. For *now*, however, do not include this contract in any past-performance section of proposals — it has not yet generated performance data we can reference.

— J. Ortega, PM